Severn Trent plan to  tarmac the road past the windsurfer car park to commence Monday the 15th of September and are expected to take 2 weeks. We will not be able to park or use this area until completed.  As this will limit parking at the Western end of our land, particularly on windy days, please use the Eastern Car park.
Information below as supplied by ST.
·         Works are anticipated to take 2 – 3 weeks to complete, consisting of 3 days planing off existing surface, 3-4 days installing kerb edgings, 2 days digging out and making good softer areas, 3-4 days surfacing.
·         The working area is to be fenced off entirely using temporary security fencing for the duration of works, this includes fencing down to the waters edge to ensure no pedestrians can gain access to the working area.
·         The pedestrian footpath running alongside the road will be closed for the first 3 days during planing and then re-opened. Visitor Experience Team to ensure adequate signs are in place to warn public that this section of footpath is closed.

Contact us

Please complete the form below and a member of staff will get back in touch with you.

Check, Clean, Dry​

All visitors and Club members should follow the Check Clean Dry programme before bringing their craft to Draycote Water and when they take their craft away.